Abstract The project implementation completed the detailed design of 2.5MW WTGS; parts trial and the whole assembly, and the factory tests of generator and deflector; and finally it completed the installation, commissioning and trial operation of the first prototype at Goldwind’s testing wind farm in Beijing. The MW-level WTGS development objective of domestic brands has been achieved, and at the same time, the WTGS international standard certificaton and on-site tesing has been completed. In 2010, the Goldwind 2.5MW WTGS begun to be put into market gradually, which strengthens the WTGS competitiveness of Chinese brands in the wind power market.
Author China Renewable Energy Scale-up Programme (CRESP), Update date 7 August 2011
Publisher
Link http://www.cresp.org.cn/english/content.asp?id=1450
Attachment Sorry, no attachments exist.
6 Renewable Energy, 6.2.0 Wind, 6.2.3 Technology Development