Pre-feasibility Study and Power Station Construction Relevant Technique Study for Jiantiao 20 MW Pilot Tidal Power Station

Abstract It is one of the sub-grant projects at the provincial level. The pre-feasibility study was carried out by the project on the tidal energy resources, capacity, building program, power generation, economy and so on of the Jiantiao 20MW Tidal Power Station in Zhejiang Province, and the pre-feasibility study report was finished. The dam construction methods were researched on and the feasible construction plan was provided. At the same time, the dam settlement was researched too to ensure dam safe.
Author China Renewable Energy Scale-up Programme (CRESP), Updated:7 July 2011
Publisher
Link http://www.cresp.org.cn/english/content.asp?id=1481
Attachment Sorry, no attachments exist.
6 Renewable Energy, 6.6 Other Renewable Sources